Crusoe Confirms Google Developer Role at Texas Campus With $2.58 Billion in Filed Building Costs
Crusoe publicly identified itself as the developer of Google's data center campus near Claude, Texas, on September 28, 2026, with six state construction registrations totaling $2.584 billion in estimated building costs and projected completion dates running through July 2027. The filings cover six buildings ranging from roughly 485,000 to 805,000 square feet each, with the first handover to Google expected in early 2027 according to a Crusoe development director. The public record does not yet confirm a signed Google lease, actual building delivery, contracted power capacity, or wind offtake terms.