Xcel Energy Battery Units Arrive at 135.5 MW Blue Lake Site, Service Due 2027
Xcel Energy reported on October 27, 2026 that battery units have arrived at its Blue Lake site in Shakopee, Minnesota, part of a three-project, 735.5 MW portfolio targeted for service by the end of 2027. The summary covers each project's capacity, permit status, and expected in-service dates, and notes that equipment arrival does not confirm installation or commissioning is complete. Capital costs, the equipment supplier, and rate recovery for two of the three projects were not established in public records.